Estimated Timeline - Phase 2
Bucksbaum Campus Construction


October

  • Site work:
    • Extend water, sewer, and electrical
    • Excavate and drive micropiles for foundations
  • Historic restoration: investigate and begin remedial repairs on historic buildings
  • Move building: lift and move historic building 150 feet on site to accommodate new site plan

-------

November

  • Set steel beams for structural walls in all buildings

-------

December

  • Install roofs on all buildings
  • Acoustic: Install concrete walls for sound isolation for new brass practice rooms

-------

JanUAry

  • Install windows in all buildings
  • Begin siding and exterior finishes
  • Frame interior walls

-------

February

  • Electrical, plumbing, and HVAC rough-in
  • Acoustic: Hang acoustic clouds and exposed ducts in rehearsal hall

-------

March

  • Insulation
  • Hang drywall
  • Install kitchen equipment
  • Install custom Skyfold room dividers in Middle School Building to divide classrooms into studios

-------

April

  • Paint and interior trim
  • Acoustic: Hang acoustic panels in rehearsal hall
  • Test kitchen

-------

May

  • Install fixtures
  • Move in office furniture
  • Acoustic testing

-------

June

  • Landscaping
  • MOVE IN